Crestron BB-1600 Back Box
Installation Guide - DOC. 5835A Back Box: BB-1600 3
Installation
There are at least two different methods of installing the BB-1600. The
construction method is preferred during the construction process. Use this
method to wall mount a Crestron Series 1600 Lectern/Wall Mount
Touchpanel to a wall stud. At this time the rooms in which the panel is to
be installed are framed and the gypsum board has not been hung. The
post-construction method is preferred for wall mounting when the rooms
are complete and the gypsum board has already been hung. The post-
construction method is also desirable when lectern mounting the panel.
Construction Method
This method requires two #6 mounting screws (or equivalent) and a drill
with bit for two #6 mounting screws. Other tools required include a #2
Phillips tip screwdriver, a socket screwdriver (length should not exceed
4.5"), a 5/16” drill bit, a #20 drill bit, and a gypsum board saw (or
equivalent). Complete the following installation procedure in the order
provided.
1. Remove necessary knockout(s) from metal electrical box.
2. Use four socket hex head screws (3/8” length), supplied, to
loosely secure two metal brackets to the back box.
3. Position the metal electrical box to the stud. If
5
/
8
" gypsum board
is used, be sure that ½" of the box protrudes from the stud as
illustrated in the metal electrical box cut away shown on the next
page.